OHL/FCC A35-26 Project Presentation
Project Highlights
A35-26 Highway 407 Station and the Northern Tunnels
- Toronto-York Spadina Subway Extension (TYSSE)
- Contractor: OHL/FCC LP
- Client: Toronto Transit Commission
- Location: Toronto, Ontario, Canada
- Budget: 357.53 million dollars CAD
- Notice of Contract Award: January 19, 2011
- Project Completion Date: October 2015
- Permanent works concrete box structure (20x150x20m) and bus terminal
- Site services: water, storm, sanitary
Highway 407 Station
Northern Tunnels
- 7.2km (3.6km each) TBM mined tunnel (6m diameter)
- 200m SEM Tunnel
- Permanent works: 2 crossover box structures, 3 emergency exit shafts, 3 cross passages SEM Tunnel
North Twin Tunnels
Tunnel Mining (100% Completado); Track Invert (70%)
TBM twin tunnel mining is 100%.
Tunnel track invert concrete work is 70%
Drive 1 (EEB4 to North Wye –100% Complete)
Drive 2 (407 to ES2 – 90% Complete)
Drive 3 3 (407 to ES3 – 20% Complete)
Highway 407 Station and Bus Terminal
33% complete
SEM Tunnel
88% complete
Running Tunnels 100%
Pocket track is 65% (Overall)
Pocket track excavation is 100%
North and South Wye Crossover Structures
North Wye (78% Completado); South Wye (84% Complete)
North Wye
Reinforced concrete box units 1500 to 1505 are complete
Unit 1506 drop shaft is 85% complete
Units 1497 to 1499 will be constructed once SEM Tunnel work is finalized
South Wye
Units 1469 to 1472 are complete
Remaining units 1473 and 1474 will start shortly
Emergency Exit Buildings
EEB4 (74%); EEB5 (94%); EEB6 (75%); EEB7 (42%)
EEB4 is 74% complete
Invert slab and first lift of walls finished
EEB5 is 94% complete
Unit 1674 drop shaft final lift currently being completed
EEB6 is 75% complete
Completed up to second lifts of walls
EEB7 is 42% complete
Hand mining to each tunnel underway.
Permanent works to commence shortly.
Cross Passage
CP5 (93%); CP6 (1%); CP7 (64%)
Cross Passage 5 is 93% complete
Cross Passage 6 is 1% complete
Dewatering has been initiated
Cross Passage 7 is 64% complete
Temporary tunnel propping installed
Hand mining to begin shortly
York University Station Siteworks
100% complete
York University Station Siteworks is 100% complete
Site has been handed over to station contractor